There is no single number — and any designer who gives you one before seeing your lot is guessing. A 5–7 unit multiplex goes through feasibility, concept design, and a coordinated permit set, and each stage takes as long as the decisions and inputs it needs. What you can control is the order: feasibility first, then concept, then permit drawings. Projects that skip the feasibility stage are the ones that stall later, when a zoning problem or a servicing constraint forces a redesign of a finished drawing set.
The stages, in order
1. Feasibility and lot read. Before any drawing starts: zoning, the as-of-right unit count, the unit sizes the zoning allows, area rents, and the typology that maximizes rent and unit mix. At this size, townhouse and stacked-townhouse layouts usually beat condo-style — less wasted lobby and elevator area, lower construction cost. This stage also flags whether MLI Select points are worth chasing: sometimes a higher points tier costs unit area and adds construction cost (an elevator, for example) beyond what the budget can carry, and a lower tier with a longer amortization is the better project.
2. Concept design. Plans, massing, and unit layouts, shaped by construction reality from the first sketch: structure, MEP routing, fire separations, and cost-aware detailing. This is where the unit mix gets scored against the MLI Select criteria — affordability, energy efficiency, accessibility — because those outcomes are locked in at design stage and cannot be value-engineered in later without losing points.
3. Permit-ready drawings. The full coordinated set for Toronto submission: architectural drawings coordinated with the structural engineer and the other consultants. The engineer’s stamp goes on the set (Expose’s drawings are issued under its professional engineer’s stamp). Completeness here is what keeps the city’s review moving — an incomplete set comes back with comments, and every resubmission costs weeks.
4. City review. Review timelines belong to the city, not the designer, and they move with the completeness of the submission and the complexity of the project. Servicing items run on their own clocks too — a new water service or sanitary connection, for example, is applied for and scheduled separately from the building permit.
What usually causes delays
Starting drawings before the lot read. A setback problem, an angular-plane limit, or a servicing constraint discovered after the drawings are done means redrawing, not revising.
Late consultant coordination. Structural, mechanical, and servicing inputs that arrive after the architectural set is finished force rework. Coordinating engineers early is the cheapest schedule protection there is.
Designing for financing after the fact. If MLI Select scoring is bolted on at the end, unit sizes or accessibility features change late — and late changes ripple through the whole set.
Undecided scope. Every open decision — unit count, typology, amenity approach — is a week the drawings cannot move. The feasibility stage exists to close those decisions before drafting starts.
How to keep your project moving
Get the lot read before you buy or commit. Score the unit mix against MLI Select at concept stage, not at permit stage. Confirm servicing early, alongside the drawings rather than after them. And start with the free step: a 20-minute MLI Select Readiness Check gives you a one-page lot and financing snapshot, including a realistic read on your project’s timeline, before you spend anything.
Related
- Multiplex design service in Toronto — 5–7 unit design planned around CMHC MLI Select financing.
- How many units can I build on my Toronto lot?
- How much does multiplex design cost in Toronto?
- 21 Winlock Park — a 5-unit Toronto multiplex designed for CMHC MLI Select
- Contact our Toronto studio