A Detailed Feasibility Example: 21 Winlock Park, North York

Investors often ask what a multiplex feasibility actually looks like in numbers. This page works through a real Expose project — 21 Winlock Park in North York — starting from its verified facts, then showing every calculation transparently, with each assumption labelled. Nothing here is presented as a promise about this project or any other: the verified facts are the project’s, and every other number is an illustrative assumption used to demonstrate the method.

The Verified Project Facts

  • Project: 21 Winlock Park, North York — a five-unit multiplex
  • Size: approximately 12,000 square feet
  • Build value: approximately $5 million
  • Financing: $4 million in CMHC MLI Select financing, recorded for five units
  • Status: permit issued and mid-build — main building permit 25 167463 (HVAC revision 25 167463 HVA 01 MS issued Aug 28, 2026); garden suite permit 26 125778 HVA 00 MS issued Aug 7, 2026. Framing inspections passed, envelope complete, interior finishes underway; completion ~Mar 2027, occupancy end May 2027.
  • Expose’s role: designer and construction consultant

That is the complete verified fact set for this project. The project is not finished, and no rental income has been verified for it.

Step 1: Derived Figures From Verified Facts

These figures are simple arithmetic on the verified facts above — no new assumptions are introduced:

Derived figureCalculationResult
Average area per unit12,000 sq ft ÷ 5 units~2,400 sq ft per unit
Build value per square foot$5,000,000 ÷ 12,000 sq ft~$417 per sq ft
Financing share of build value$4,000,000 ÷ $5,000,00080%
Equity gap before land and soft costs$5,000,000 − $4,000,000~$1,000,000

The equity gap matters because it is the money the project needs beyond the verified financing, before land, soft costs, and financing fees are counted. Feasibility work exists to test whether the rental income supports carrying that gap — before design, not after.

Step 2: The Method — Land First, Then Rents, Then Typology

The feasibility followed Expose’s standard order:

  1. Land: the lot was tested for a five-unit minimum and for the unit sizes as-of-right zoning allows.
  2. Rents: area average rents were checked to confirm the project was worth building.
  3. Typology: the unit mix was chosen to maximize rent — townhouse and stacked-townhouse forms were preferred over condo-style layouts at this size, because they deliver better rents at the same unit size with less wasted lobby, elevator, and common area, and lower construction cost.

Step 3: Illustrative Rent Scenarios (Assumptions, Not Verified Facts)

The rent figures below are ILLUSTRATIVE ASSUMPTIONS used to demonstrate sensitivity analysis. They are not market data for North York, and they are not the project’s actual rents. Gross annual rent is five units multiplied by the monthly rent multiplied by twelve, shown before vacancy, operating costs, taxes, and financing costs.

ScenarioIllustrative average rent per unit per monthGross annual rent, 5 units
Low$2,400$144,000
Base$2,800$168,000
High$3,200$192,000

A $400 monthly difference per unit moves gross annual rent by $24,000 across five units. Small rent errors compound across a building, which is why the rent check comes before the design is locked.

Step 4: Illustrative Operating Picture (Assumptions, Not Verified Facts)

To show how gross rent becomes operating income, we apply one further ILLUSTRATIVE ASSUMPTION: operating costs (maintenance, insurance, property tax, management, vacancy allowance) at 35% of gross rent. This ratio is an example only — a real project uses its own cost schedule.

ScenarioGross annual rentLess 35% illustrative operating costsIllustrative net operating income
Low$144,000−$50,400$93,600
Base$168,000−$58,800$109,200
High$192,000−$67,200$124,800

Step 5: Illustrative Cost Sensitivity (Assumptions, Not Verified Facts)

The verified build value is approximately $5 million. The table below shows how a 10 percent move in construction cost changes the equity gap, holding the verified $4 million financing constant:

ScenarioIllustrative build valueEquity gap vs. $4M financing
10% under$4.5 million$500,000
Verified figure~$5 million~$1,000,000
10% over$5.5 million$1,500,000

A 10 percent construction cost overrun moves the equity requirement by $500,000 on a project of this size. Cost discipline is a feasibility input, not an afterthought.

Step 6: The Financing-Tier Trade-Off

A further judgement the feasibility tests is whether chasing a higher MLI Select points tier is worth it. A higher tier can extend amortization, but reaching it can cost unit area or add construction cost — an elevator, for example — beyond what the loan and budget can carry. In such a case, deliberately accepting 40-year amortization can be the better decision. That trade-off is tested in the feasibility, with the project’s own numbers, not discovered during construction.

What This Example Teaches

  • Test the land before the design. A lot that cannot support five units changes the entire financing strategy.
  • Test rents before the unit mix. A $400 rent error per unit is a $24,000 annual error across five units.
  • Test costs before the loan. A 10 percent overrun is $500,000 of additional equity on a project of this size.
  • Test the tier, don’t chase it. A higher points tier that costs rentable area or adds an elevator can be worth less than the amortization it buys.

Frequently Asked Questions

Are the rents in this example real?

No. The rent figures are ILLUSTRATIVE ASSUMPTIONS, labelled as such. Real rents must be checked for the specific area and unit type at the time of the assessment.

Is 21 Winlock Park finished and rented?

No. The permit is issued and the building is mid-build (framing inspections passed, envelope complete, interior finishes underway), with completion expected ~Mar 2027. This example uses its verified design and financing facts to demonstrate the feasibility method.

Can I get a feasibility example for my own lot?

Yes. A pre-purchase feasibility assessment applies this same method — land, rents, typology, cost sensitivity, and tier trade-offs — to your specific property.

Does MLI Select financing cover the whole build cost?

No. In this example, $4 million of financing against an approximately $5 million build value leaves an equity gap of approximately $1 million before land and soft costs. Your lender confirms the actual structure.

Why does typology matter so much to the numbers?

Because at five to seven units, common area and vertical circulation eat rentable area. A townhouse or stacked form keeps more of the building rentable, which is what the rent math rewards.